Monday, May 26, 2008

Last week


Most of the windows are in. House is wrapped in Tyvek, reading for siding and roof is ready for steel galvalume roof. Also the frame for the deck on the south side of the house is up now, ready for planking and temporary rail.

This coming week the rest of the windows and exterior doors go in, and perhaps deck floor. Also Tuck is preparing to move a small travel trailer to the site so he doesn't have to drive back and forth so often.  Its an old Layton travel trailer he found on ebay - 70s harvest gold decor but very serviceable. We'll be selling it after the house is done if anyone is interested.